9. Remove the input drive assembly. Slide both belts off of the ends of the input drive
assembly.
10. Hold the replacement input drive assembly at it’s mounting position and slide the input belt
over and past the pillow block bearing on the left side of the input drive assembly. Slide the
step belt over and beyond the pillow block bearing on the right side of the input drive
assembly.
11. Replace the input drive assembly. Torque the four bolts that mount the input drive assembly
to 500 inch pounds.
Diagram 7.16 - Drive Unit Alignment
12. Place the input belt and step up belt in place on their pulleys. Tighten both belts enough so
that they don’t slip and are roughly aligned. The tensioning and alignment of the belts will be
completed in a later step.
13. Replace the magnet assembly per procedure 7.20.
14. Complete the installation, drive belt alignment and tensioning per Procedure 5.3.
15. Replace the crankarms per Procedure 7.12. The crankarms must be parallel to the frame
uprights. See Diagram 7.16. If necessary loosen the four drive unit mounting bolts, align the
drive unit and torque the drive unit mounting bolts to 500 inch pounds.
Crankarm
Frame Upright